Incident History for British Columbia Institute of Technology

A complete log of all past incidents, outages, and scheduled maintenance.

Filter by status

applies to the 15 loaded
Power shutdown affecting Network Services at specific BCIT buildings

Completed

Affected Components

Network Services

Completed

16 hours ago

Scheduled power shutdown maintenance affecting Network Services at specific BCIT buildings has been completed.

Under Maintenance

20 hours ago

Scheduled power shutdown maintenance is now in progress at specific BCIT buildings, affecting Network Services.

Scheduled For

Nov 22, 2026, 11:45 AM UTC

Scheduled

21 hours ago

Scheduled power shutdown maintenance for specific BCIT buildings begins in 60 minutes, affecting Network Services.

Scheduled For

Nov 22, 2026, 11:45 AM UTC

Wireless network maintenance in SW01 building

Completed

Affected Components

Network Services

Completed

on Nov 22, 2026

Scheduled wireless network maintenance in the SW01 building has been completed.

Under Maintenance

on Nov 21, 2026

Scheduled wireless network maintenance in the SW01 building is now in progress.

Scheduled

on Nov 21, 2026

Wireless network maintenance in the SW01 building begins as scheduled in 60 minutes.

Scheduled For

Nov 21, 2026, 4:00 PM UTC

Power shutdown affecting Network Services in specific buildings

Completed

Affected Components

Network Services

Completed

on Nov 21, 2026

Scheduled power shutdown maintenance affecting Network Services in specific buildings has been completed.

Under Maintenance

on Nov 21, 2026

Scheduled power shutdown maintenance is in progress for specific buildings, affecting Network Services.

Scheduled For

Nov 21, 2026, 4:45 AM UTC

Microsoft Outlook email outage affecting BCIT employees

Resolved

Affected Components

BCIT Employee EmailConference Rooms - Video SystemsMSTeams VoiceMicrosoft 365

Resolved

on Nov 14, 2026

Microsoft service outage affecting BCIT email and related services has been officially resolved.

Monitoring

on Nov 13, 2026

Microsoft services including Outlook email are gradually being restored, though some users may still see delayed delivery.

Monitoring

on Nov 13, 2026

Microsoft services including Outlook email are gradually being restored, though some users may still see intermittent access issues or delayed delivery.

Identified

on Nov 12, 2026

Microsoft has identified the issue and is testing a solution; the outage may affect Exchange Online, Teams, SharePoint, Copilot and Defender at BCIT.

... and 1 more update(s). Click to view the full timeline.

Wireless network maintenance completed at all campuses

Completed

Affected Components

Network Services

Completed

on Nov 1, 2026

Scheduled wireless network maintenance across all campuses has been completed.

Banner maintenance completed

Completed

Affected Components

BCIT Central LoginBanner 9Banner Self-ServeMain BCIT WebsiteNetwork ServicesmyBCIT Website

Completed

on Nov 1, 2026

Scheduled Banner maintenance has been completed, restoring affected BCIT services.

Under Maintenance

on Nov 1, 2026

Scheduled wireless network maintenance is currently in progress across all campuses, affecting Network Services.

Under Maintenance

on Nov 1, 2026

Scheduled Banner maintenance is currently in progress, affecting the BCIT website, central login, Banner Self-Serve, Banner 9, and myBCIT.

Scheduled

on Nov 1, 2026

Scheduled wireless network maintenance across all campuses begins in 60 minutes, affecting Network Services.

Scheduled For

Nov 1, 2026, 1:00 AM UTC

... and 2 more update(s). Click to view the full timeline.

AppsAnywhere offline due to vendor outage

Identified

Affected Components

AppsAnywhere

Identified

on Oct 30, 2026

AppsAnywhere is offline for all higher education institutions due to a vendor outage; IT Services is working with the vendor.

Data Centre Shutdown Affecting BCIT Services

Completed

Affected Components

AppsAnywhereBanner 9Banner Self-ServeNetwork ServicesmyBCIT Website

Completed

on Oct 25, 2026

The scheduled data centre shutdown maintenance has been completed, restoring network services, Banner, AppsAnywhere, and the myBCIT website.

Scheduled For

Oct 24, 2026, 12:00 AM UTC to Oct 25, 2026, 12:00 AM UTC

Under Maintenance

on Oct 25, 2026

Scheduled data centre shutdown is now in progress, affecting network services, Banner, AppsAnywhere, and the myBCIT website.

Scheduled For

Oct 25, 2026, 1:00 AM UTC to Oct 26, 2026, 1:00 AM UTC

Scheduled

on Oct 25, 2026

Scheduled data centre shutdown begins in 60 minutes, affecting network services, Banner, AppsAnywhere, and the myBCIT website.

Scheduled For

Oct 25, 2026, 1:00 AM UTC

AppsAnywhere outage resolved

Resolved

Affected Components

AppsAnywhere

Resolved

on Oct 22, 2026

AppsAnywhere is now available after unplanned maintenance, and BCIT IT Services will continue monitoring for issues.

Identified

on Oct 21, 2026

AppsAnywhere is offline while critical PHP security vulnerabilities are addressed, with BCIT IT Services monitoring and updates pending.

Flexible Learning Registration delayed

Monitoring

Affected Components

Banner Self-ServeMain BCIT Website

Monitoring

on Oct 22, 2026

BCIT continues monitoring the website and Banner Self-Serve outage, with registration still delayed.

Investigating

on Oct 21, 2026

BCIT website remains offline for critical security updates, and Winter term registration is still delayed while investigation continues.

Investigating

on Oct 21, 2026

BCIT website is temporarily offline for critical security updates, and Winter term registration is delayed until further notice.

Investigating

on Oct 21, 2026

Flexible Learning Registration is delayed until October 22, 2026, and the issue remains under investigation.

Linux maintenance affecting BCIT services

Completed

Affected Components

BCIT Central LoginBCIT Employee EmailBanner 9Banner Self-ServeMain BCIT Website

Completed

on Oct 11, 2026

The scheduled Linux maintenance has been completed, restoring the main BCIT website, central login, Banner Self-Serve, Banner 9, and employee email.

Under Maintenance

on Oct 11, 2026

Scheduled Linux maintenance is currently in progress, affecting the main BCIT website, central login, Banner Self-Serve, Banner 9, and employee email.

Network Maintenance Completed

Completed

Affected Components

Network Services

Completed

on Oct 10, 2026

Scheduled network maintenance for British Columbia Institute of Technology has been completed.

Under Maintenance

on Oct 10, 2026

Scheduled network maintenance is currently in progress and updates will be provided as necessary.

Completed

on Oct 9, 2026

Scheduled network maintenance has been completed.

Completed

on Oct 8, 2026

Scheduled Network Services maintenance has been completed.

... and 3 more update(s). Click to view the full timeline.

Network maintenance starting soon

Under Maintenance

Affected Components

Network Services

Under Maintenance

on Oct 9, 2026

Scheduled network maintenance is now in progress and updates will follow as needed.

Scheduled For

Oct 9, 2026, 5:00 AM UTC

Scheduled

on Oct 9, 2026

Network maintenance is scheduled to begin in 60 minutes on October 8 at 22:00 PDT.

Scheduled For

Oct 9, 2026, 5:00 AM UTC

Network Services maintenance starting soon

Scheduled

Affected Components

Network Services

Scheduled

on Oct 8, 2026

Scheduled network maintenance for Network Services begins in 60 minutes.

Scheduled For

Oct 8, 2026, 5:00 AM UTC

Wi-Fi and VPN connectivity impacted

Resolved

Affected Components

GlobalProtect VPNNetwork Services

Resolved

on Oct 7, 2026

The Wi-Fi and VPN incident has been resolved.

Investigating

on Oct 7, 2026

Connectivity to campus Wi-Fi and GlobalProtect VPN is impacted; investigation and repairs are underway.

    Incident History for British Columbia Institute of Technology